Review changes to the room before assuming the unit is oversized
A room’s duty can change when equipment is removed, added or rearranged. Sensor location, air movement and the way several cooling units interact can also affect the operating picture. Oversizing is one possible design question, but repeated starts alone do not prove it. Preserve the room layout and change history so the investigation can consider the actual application.
If a rack move or equipment retirement preceded the starts, tell service what changed and when. If one unit is in alarm while the room warms or the normal standby unit is unavailable, escalate under the site’s incident plan. Keep any later capacity study separate from the immediate task of restoring dependable cooling.