What evidence should an immersion-cooling purchase include?
Request records identifying the exact hardware configuration and immersion fluid, the scope and conditions of the compatibility evidence, the supplier’s written approval and the applicable coverage terms. Keep technical evidence and commercial coverage in separate columns. A test result, a product approval and a warranty document establish different things; none should be silently substituted for another.
Separate test evidence, supplier approval and coverage
The Open Compute Project (OCP) June 2026 Server Component Immersion Material Compatibility Testing document explicitly limits its scope. Its guidance does not establish certification, fitness for use or service life. It also notes that results depend on the environment, exposure and test conditions. A reference to that document is therefore a starting point for questions about the actual evidence.
OCP’s separate warranty guidelines discuss equipment, fluids, responsibilities and coverage. They are not the terms offered by a particular supplier on your purchase. Request the governing documents from the parties making the commitments.
| Record | Question it helps answer | What to request next |
|---|---|---|
| Material or component test report | What was evaluated, under which conditions, and with what recorded outcome? | The tested identities, method, scope and limitations |
| Supplier approval statement | Does this supplier approve the proposed combination and use? | Written confirmation tied to the purchase configuration |
| Warranty / support terms | What commitment is offered, by whom, under which conditions? | Applicable terms, exclusions, responsibilities and claim contact |
Make the hardware and fluid identifiable
Build the register from the proposed bill of materials. Give each record a configuration, part or assembly identifier rather than a broad label such as “GPU server.” Ask the supplier which revisions and substitutions its approval includes. Record the fluid product identity with the same care.
Ask whether the evidence concerns a material sample, a functional component or the assembled system. OCP’s component-testing paper distinguishes component/material evaluation from broader system reliability work. A record for one level needs an explicit applicability explanation before the purchasing team uses it for another.
Keep document names and revisions visible. “Approved by vendor” becomes much more useful when the row states which vendor, the reference that contains the approval, the combination it covers and the written question still open. The register should let a colleague retrieve the record without repeating the original conversation.
References: [1]
Ask each supplier to define its own commitment
Attach the terms offered for the hardware, immersion fluid and cooling equipment to their respective rows. Ask which party receives a claim involving more than one supplied item and what records that party expects. Keep a technical approval separate from an assurance about who will pay for a repair.
Record stated exclusions and customer responsibilities in the coverage column using a short reference to the actual clause or document. Do not turn a sales email saying “supported” into a broader commitment than it contains. Where documents disagree or their effect is uncertain, send that specific question to the responsible supplier and the procurement or legal reviewer.
The purpose is to make the purchasing evidence reviewable. This guide does not determine whether coverage is valid, invalid or legally enforceable. Those conclusions require the applicable documents and an appropriate review of the actual transaction.
References: [2]
Worked example: a component substitution reopens one row
In this fictional purchase, a supplier’s statement names server configuration H-1 with fluid F-1. A supporting report lists network adapter revision A. Before delivery, the proposed bill of materials changes to adapter revision B while retaining the server’s marketing name. None of these identifiers refers to a real product or Airplex project.
The buyer can identify the difference without declaring the new adapter compatible or incompatible. The useful question is whether the existing evidence and supplier approval explicitly include revision B. Until that is answered, mark applicability unresolved for the changed configuration.
Now suppose the hardware supplier confirms technical approval for revision B, but its reply says nothing about the coverage document. Close the technical question only to the extent supported by the reply, and keep the commercial question open. Two records can move at different speeds. The register should show that distinction instead of reducing everything to a single green check.
| Item | Evidence in hand | Question still open | Owner to respond |
|---|---|---|---|
| Original H-1 / F-1 combination | Supplier statement and referenced report | Confirm the purchase matches the stated scope | Hardware / system supplier |
| Adapter revision A → B | Changed bill of materials | Does the technical approval include B? | Issuer of the approval |
| Coverage after the change | Existing coverage document | Which written terms apply to the changed combination? | Party offering coverage / procurement reviewer |
Keep the evidence attached to future changes
Ask at purchase who will review later component or fluid substitutions and how that review will be recorded. Save the accepted bill of materials, applicable supplier statements and coverage documents together. When a change is proposed, compare it with that accepted set instead of relying on the original product name.
Keep the immersion-fluid register separate from the facility water-loop records. The project may need both, but a water-quality responsibility schedule does not answer whether a server component and immersion fluid combination has supplier approval.
For a NYC or Northern New Jersey facility project, use the resulting record to clarify where the equipment supplier’s responsibilities meet the mechanical work package. Ask which documents each provider needs for its task. Share confidential configurations through the agreed project channel, and keep public inquiries to the equipment category and decision needed.
Put this guide to work
Immersion compatibility and coverage register
Complete separate technical and coverage columns for each combination. Include document revisions, scope and exclusions. In the final column, name the issuer or contact and the written response needed for any proposed change.
Open each item to add your notes, then download the CSV to keep a copy. This tool does not save or submit your entries; do not rely on your browser restoring them.
Server configuration / bill of materials
Component or assembly evidence
Fluid product and applicable approval
Tank / cooling-equipment interface
Replacement or substitution
Cross-supplier claim / support responsibility
Continue with a related decision
Questions & answers
Does a material-compatibility test prove a complete server is approved?
Only the stated scope of the evidence can support that conclusion. Identify what was tested and ask the system supplier how that evidence applies to the proposed assembly and use. OCP’s component-testing guidance specifically avoids treating its results as certification, guaranteed fitness or established service life.
Does immersion automatically void or preserve a warranty?
This guide makes neither determination. Request the terms that apply to the exact equipment, fluid combination and use, then have unresolved wording reviewed by the responsible supplier and procurement or legal team. A general industry guideline cannot establish the coverage offered in an individual transaction.
What if a replacement part keeps the same marketing name?
Compare the actual part and revision identifiers with the approved configuration. Ask the issuer whether its evidence and approval include the replacement, and record the response. A familiar product name does not resolve a revision question or establish that commercial terms remain the same.
Sources & technical references
- OCP: Server Component Immersion Material Compatibility Testing
Version 1.5, June 2026; sections 1.1 and 1.2 establish scope and limits. Reviewed November 16, 2026. Actual PDF title used rather than the search extraction’s legacy title.
- OCP: Warranty Guidelines for Immersion Cooled Technology Components, Equipment and Systems
Revision 1.0, April 26, 2024; equipment/fluid coverage and responsibility context. Reviewed November 16, 2026. No legal template or jurisdictional rule is reproduced.
NYC & Northern New Jersey
Bring the equipment evidence into the scope discussion
Airplex Mechanical’s Critical Cooling Division can discuss immersion-related mechanical work for NYC and Northern New Jersey facilities. Identify the proposed system, responsible suppliers and the interface questions that need to be resolved.