Start here
Does direct-to-chip cooling remove the room’s air-cooling duty?
Not necessarily. Direct-to-chip cooling can leave a substantial air-cooling duty. The result depends on the exact IT configuration, components served by liquid, equipment that remains air cooled and where the liquid system rejects heat. Obtain configuration-specific vendor evidence and account for each path separately. A liquid heat-capture percentage is not, by itself, a basis for reducing or retiring room cooling.
Ask what the percentage actually covers
Lenovo’s Neptune Direct Water-Cooling Standards describes configurations that retain an air-cooling requirement. Its examples attach heat extraction to particular equipment arrangements. They establish that residual duty exists; their percentages are not a default for every direct-to-chip server.
For the proposed purchase, request the full configuration identifier, the covered components, the operating condition and the definition of the reported heat split. Ask whether the denominator is component power, server input or a complete rack. A percentage with an unclear denominator is not ready to multiply by the room’s electrical load.
Keep evidence types separate. A vendor selection document, a design assumption and an operating measurement answer different questions. Record which one you have, its revision or time period, and whether the technical reviewer considers it applicable to the proposed state.
References: [1]
Follow the heat beyond the cold plate
The conceptual paths below show the distinction between collecting heat and removing it from the room. The Open Compute Project (OCP) liquid-distribution guidance describes technology and facility interfaces, including the coolant distribution unit (CDU). The selected project documents must identify the actual arrangement.
For a liquid-to-liquid arrangement, the reviewer needs evidence for the facility receiving path. CoolIT’s AHx180 product documentation provides an example of the alternative: a liquid-to-air CDU that sends captured heat into data-center air. If a proposed unit rejects into this same room, that heat still enters the room-air balance. Ask the supplier to confirm the discharge location and treatment of equipment losses before assigning a room-load reduction.
| Heat origin | Collection path | Receiving path | Evidence to attach |
|---|---|---|---|
| Covered IT components | Cold plates → technology liquid | Liquid-to-liquid CDU → facility system → heat rejection | Configuration heat split and confirmed receiving-system boundary |
| IT components outside the liquid path | Component heat → rack air | Room or other documented air-cooling path | Vendor air-side requirement for the selected configuration |
| Unconverted servers / network equipment | Equipment heat → air | Existing documented air-cooling path | Equipment list and consistent load basis |
| Alternative CDU rejecting into this room | Technology liquid → liquid-to-air CDU | Heat returns to room air | CDU architecture, discharge location and losses |
Worked example: allocate the same load once
Assume a fictional group of four racks, each using 60 kW at the stated condition. For this example only, assume configuration-specific evidence assigns 45 kW per rack to liquid and 15 kW to air. The remaining air-cooled IT contributes 30 kW on the same load basis. These are invented teaching values, not typical capture fractions or Airplex results.
The four racks total 240 kW. Their liquid allocation is 4 × 45 = 180 kW; their air allocation is 4 × 15 = 60 kW. Adding the other IT gives 90 kW assigned to air and 180 kW assigned to liquid, accounting for the same 270 kW of IT input once.
If the 180 kW liquid path transfers to a facility system outside this room-air boundary, the example leaves 90 kW of identified IT air duty. If that liquid path instead rejects into the same room, the identified IT contribution to room air becomes 270 kW. CDU losses and other room gains remain separate, unquantified items in both cases.
Neither result is a room-cooling equipment selection. The example omits other gains, operating ranges, the spatial distribution of heat and the project’s availability requirements. Its purpose is to show why the same captured heat cannot be subtracted from the room and then forgotten at its discharge point.
| Equipment group | Total input basis | Assigned to liquid | Assigned directly to air |
|---|---|---|---|
| Four selected racks | 4 × 60 = 240 kW | 4 × 45 = 180 kW | 4 × 15 = 60 kW |
| Other air-cooled IT | 30 kW | 0 kW | 30 kW |
| Identified IT total | 270 kW | 180 kW | 90 kW |
| CDU losses and other room gains | Not quantified | To be assigned | To be assigned |
Keep an unknown separate from a zero
If the supplier has not supplied the air-side requirement for a configuration, mark its allocation unresolved. Do not fill the cell using a percentage from another model. Likewise, a missing entry for network equipment or room-located losses is a question to close, not evidence that the contribution is zero.
Review whether figures describe the same condition. Mixing one rack’s maximum input with another rack’s measured average creates a total with an unclear meaning. Use a consistent basis or label the mismatch so the reviewer can resolve it.
A useful completed record shows the allocation, the source and the receiving path on one row. Where the row remains incomplete, name the document or supplier response needed. This makes the uncertainty specific enough to act on.
Use the allocation to frame the next review
Send the completed evidence record to the team responsible for the room’s cooling assessment. Ask which duties remain in each operating state and which additional information is needed to assess the air system. A total in kW does not describe where the remaining air-cooled components are located or how their air reaches them.
For a staged conversion, create a separate record for the mixed configuration that will actually operate. Keep the installation sequence in the retrofit phase plan and the heat-allocation evidence here. Any operating change belongs to the site’s authorized technical process; this worksheet provides no instruction to switch off cooling or adjust controls.
Put this guide to work
Residual-air-duty evidence record
Use one row per exact configuration or separate heat source. Enter the operating basis and document revision with each value. Keep unresolved values blank and describe the missing evidence in the last column; do not substitute a generic capture percentage.
Open each item to add your notes, then download the CSV to keep a copy. This tool does not save or submit your entries; do not rely on your browser restoring them.
Selected direct-to-chip configuration
Second configuration / rack group
Unconverted servers
Network / storage equipment
CDU losses / discharge boundary
Other room gains
Continue with a related decision
Questions & answers
Can we apply a published 80% capture figure to the whole room?
Only evidence applicable to the exact equipment and denominator can support that calculation. A figure for selected server components cannot silently become a fraction of all room IT power. Identify the covered configuration, remaining equipment and receiving heat path before building an allocation.
Does adding a rear-door heat exchanger remove every remaining air duty?
The project needs evidence for what the selected arrangement captures and where it rejects that heat. Record the rear-door contribution and its boundary without counting the same heat twice. Other equipment or room gains may remain outside that arrangement; the equipment name alone does not establish the complete result.
Is residual-air duty the same as the total room cooling load?
No. Residual duty refers to heat remaining in an air path after a defined liquid allocation. A complete room assessment also needs the other applicable gains, operating conditions and cooling requirements. Use the existing heat-load resource for total-load context and this record for the evidence behind the split.
Sources & technical references
- Lenovo Press LP2018: Lenovo Neptune Direct Water-Cooling Standards
Published September 13, 2024; configuration examples include residual air duty. Reviewed November 16, 2026. No vendor capture percentage is adopted as a general rule.
- OCP: Data Center Liquid Distribution Guidance & Reference Designs
Revision 1.0, January 8, 2024; technology/facility interfaces. Reviewed November 16, 2026. The heat-allocation diagram and numbers here are original illustrations.
- CoolIT Systems: AHx180 liquid-to-air CDU
Manufacturer description explicitly identifies rejection of captured heat into data-center air. Reviewed November 16, 2026; architecture example only, without adopting product capacity or availability claims.
NYC & Northern New Jersey
Connect the IT evidence to the facility scope
Airplex Mechanical’s Critical Cooling Division can discuss direct-to-chip and facility air-cooling needs in NYC and Northern New Jersey. Bring the configuration, heat-path records and the decision the project team needs to resolve.
Discuss the remaining cooling dutyCall (347) 627-7146