Make the measured record understandable

How to Read an HVAC Test and Balance Report

A test and balance report becomes useful when you can connect each measurement to a system, a design requirement and a test condition. Start with those connections before looking for a pass or fail.

Airplex Mechanical resources Reviewed November 16, 2026

Start here

What should you check in a test and balance report?

Identify the report revision, tested scope and system setup. Match equipment and terminal IDs to the drawings, compare design and measured values in the same units, and read the remarks and unresolved-item list. The applicable project criteria govern acceptance; a percentage difference alone does not establish compliance or explain the cause of a shortfall.

Check which document you have

Look for the project, date, revision and report status. A preliminary survey, readiness report and final test, adjust and balance report can answer different questions. Keep the report's own description in your review notes rather than calling every airflow sheet a final TAB report.

NEBB's report guidance calls attention to system setup, unique equipment identification, instrument information and noted deficiencies. It also distinguishes a certified TAB report from other project records. Use those as document-reading principles; confirm the standard and project requirements that apply to the actual report.

References: [1]

Find the test condition and the design basis

Locate the setup narrative before comparing values. Which operating mode was established? Which systems were available? Are limitations or excluded areas identified? If the report covers one configuration, do not assume it demonstrates every occupied, unoccupied or emergency mode.

Then identify the design source. Check the drawing or schedule revision named by the report and the units in each column. CFM describes cubic feet per minute of air; GPM describes gallons per minute of liquid. Pressure, temperature, fan speed and electrical readings are different quantities and should not be compared as though they were airflow.

A reviewer should be able to follow an equipment ID from the summary to its data sheet and serving-area drawing. If AHU-2 was renamed during the project, request the mapping. Otherwise a technically complete table can remain impossible for the building team to use.

Annotated sample: what the numbers do and do not say

The following excerpt is invented for this guide. It is not a certified form or an Airplex test record. Hypothetical setup: AHU-X is reported in the project's designated cooling test mode on the same test date. The designer's current schedule is the stated basis; acceptance criteria are not supplied in this example.

Fictional air-system report excerpt; all airflow values are CFM
ItemDesignRecordedDifferenceReview note
AHU-X supply4,0003,800−5%Ask where and how total supply was measured and which criterion applies.
Terminal X-1500450−10%Read the terminal remark and compare with the project's required range.
Terminal X-2500520+4%Above design does not automatically mean acceptable or better.
Terminal X-3300Not measuredNot calculableThe example remark says access unavailable; keep it unresolved.
Outdoor-air intake600Not reportedNot calculableTotal supply does not establish the missing outdoor-air quantity.

Turn each sample finding into a precise question

For AHU-X, ask for the referenced measurement method and setup rather than guessing which component caused the difference. For Terminal X-1, ask whether a remark explains the result, whether the required range is documented and whether corrective work or retesting remains open.

For Terminal X-3, ask who can resolve access and what evidence will close the unmeasured item. Do not enter zero in a spreadsheet merely because the report cell is blank. Zero is a numerical result; ‘not measured’ describes missing evidence.

For the outdoor-air intake, request the relevant record if that quantity belongs to the tested scope. The 3,800 CFM total-supply reading cannot fill the gap because it may include recirculated air. If outdoor-air measurement was excluded, retain the exclusion and identify who owns the remaining verification.

Keep correction and acceptance traceable

Create one review item per unresolved question and reference the report page, equipment ID and drawing revision. Separate a missing document from a measured deviation. Their next actions differ: one needs an explanation or record, while the other may need technical evaluation and corrective work.

Request a named response, the supporting document and any revised measurement after a correction. Keep the earlier report so the revision trail remains clear. The project team responsible for acceptance should decide whether the evidence satisfies the actual requirements.

Airplex can discuss mechanical findings within an agreed service scope. A required independent or certified TAB report remains the responsibility of the appropriately qualified reporting provider. This guide does not claim that Airplex issues NEBB-certified reports or that a TAB report alone commissions the entire building.

References: [1]

Put this guide to work

TAB report question and closure register

Add the page and equipment reference to each issue. Preserve missing measurements as unknown, and close an item only when the responsible reviewer has the required evidence.

Open each item to add your notes, then download the CSV to keep a copy. This tool does not save or submit your entries; do not rely on your browser restoring them.

Report revision, status and tested scope
Report revision, status and tested scope
System setup or operating mode
System setup or operating mode
Design drawing / schedule revision
Design drawing / schedule revision
Equipment or terminal identification gap
Equipment or terminal identification gap
Measured deviation needing explanation
Measured deviation needing explanation
Unmeasured or inaccessible item
Unmeasured or inaccessible item
Instrument or measurement-method question
Instrument or measurement-method question
Corrective work and retest record
Corrective work and retest record

Continue with a related decision

Questions & answers

Is every reading within 10% automatically acceptable?

No. Use the criteria and test conditions applicable to the project and system. This guide calculates differences without applying a universal tolerance.

Can I add every terminal reading and compare it with the fan total?

First confirm they describe the same system, operating condition and measurement basis. Ask the report author to explain differences and any applicable limitations rather than assuming an unmatched sum proves leakage or a faulty fan.

Does a TAB report prove that all controls and operating modes work?

It documents the work and conditions within its scope. Review commissioning and functional-testing requirements separately; do not assume that an airflow measurement demonstrates every control sequence.

Sources & technical references

  1. NEBB: TAB Reports

    Accessed November 16, 2026. The article discusses the 2019 ninth edition. Used for report identification, setup, measurement records, deficiencies and certification boundaries; it is not a statement of the current edition or universal project tolerances.

NYC & Northern New Jersey

Bring the report page and the unresolved question

Share the relevant report section, equipment ID and known project requirement with Airplex Mechanical to discuss the mechanical service issue identified by the evidence.